7 May 2022
News
Removal of Trees and roots to increase parking area size
Removal of Trees and Branches to allow placement of Container offices and walkway
Groundworks and installation of G5 container footings
Placement of Temporary Office Units
Application of SS60 Bitumen Prime
Installation of walkway framework for decking and roofing
Installation of Septic tank and Sewer lines
Installation of walkway roof sheeting
Composite Decking and Handrail Installation
Installation of Covered Viewing Deck
Project Completed